The Commissioning phase involves inspection and testing of the connection facility to prepare for In-Service. |
|
|
|
|
 |
|
Hydro One and the customer finalize the Transmission Connection Agreement (TCA) including the Operating Schedule, transmission tariffs, high-voltage equipment data and special connection considerations. The TCA must be executed before the customer's facilities are allowed to be placed into service. |
|
|
|
|
 |
|
Hydro One facilities are commissioned. Hydro One notifies the IESO of equipment ready for operation. |
|
|
|
|
 |
|
Customer submits Commissioning Plan 45 days prior to the In-Service date for review and comments. Customers performs and completes commissioning activities on customer-built facilities, including the submission of the COVER to Hydro One and the IESO. |
|
|
|
|
 |
|
If Hydro One is to own the customer-built Contestable portions of the project, the transfer takes place on the In-Service date. |
|
|
|
|
|
 |
|
Connection to Hydro One's transmission grid is completed. |
|
|
|
|
|
|
 |
|
Customer submits final "As Built" Connection documents and Station Single Line diagrams within 60 days of connecting to Hydro One. |
|
|
|
|
|
|
 |
|
Hydro One will revise the CCRA to reflect actual costs within 180 days of connection and will provide to the customer with the final invoice if applicable. |
|
|
|
|
|
|
 |
|
Connection Process is complete. |
|