Construction Approvals and Permits

Below is a list of permits and approvals for the Bruce to Milton Project:

Name of Permit

Relevant Legislation

Issuing Authority

Description

Status

Federal Permits and Approvals

Letter of Exemption

 

Navigable Water Protection Act

 

Transport Canda

 

  • Letters of Examption were required for four transmission line crossings of navigable waterways

Obtained

 

Aeronautical Obstruction Clearance for Height Hazards

 

Aeronautical Act

 

Transport Canda

 

  • Aeronautical Clearance may determine whether or not visual marking is necessary for towers and conductors to ensure safe aircraft navigation. Markings are usually only required for structures over 90 m in height

Ongoing

 

Land Use Submission

 

 Aeronautical Act

 

 NAV Canada

 

  • A Land Use submission and evaluation is required to ensure that transmission lines and towers do not interfere with aircraft navigation services provided by NAV Canada

Ongoing

 

Provincial Permits and Approvals

Land Use and Encroachment Permits for Provincial Highways (conductor crossings)

 

Provincial Highways Act

 

Ministry of Transportation

 

  • Permits are required to cross Provincial Highways with conductors and for new tower locations

Ongoing

 

Encroachment Permit for Provincial Highways (access roads)

 

Provincial Highways Act

 

Ministry of Transportation

 

  • Permits are required to install entrances from Provincial Highways to Project access roads

Approximately 50 per cent obtaned

 

Commercial Access Permit for Upgrades of Access Roads from Provincial Highways

 

Provincial Highways Act

 

Ministry of Transportation

 

  • Permits are required to upgrade entrances from Provincial Highways to Project access roads

 Ongoing

 

Permit

 

Endangered Species Act

 

Ministry of Natural Resources

 

  • Permits are required for removal of two butternut trees and affected habitat of Redside Dace (a fish species)

 Ongoing

 

Development Permit/Letter of Authorization

 

 Fisheries Act

 

Conservation Authority/Fisheries and Oceans of Canada

 

  • Permits and/or letters of authorization are required for installation of culverts where fish habitat may be affected

90 per cent obtained

 

Development Permit

 

Conservation Authorities Act O.Reg 97/04 Generic Regulation and "Regulation of Development, Interference with Wetlands and Alteration to Shorelines and Watercourses"

 

Conservation Authority

 

  • Hydro One is exempt from this regulation, but continues to engage relevant Conservation Authorities in the construction process

Not required

 

Work Permit

 

Public Lands Act

 

Ministry of Natural Resources

 

  • This permit is not required since the Bruce to Milton Project does not cross Crown land

Not required

 

Development

 

Niagara Escarpment Planning and Development Act

 

Niagara Escarpment Commission

 

  • Following issuance of a permit, an appeal was launched, and a decision on the appeal was deferred to the Minister of Natural Resources. A decision is anticipated in the near future

Ongoing

 

Municipal/Other Permits and Approvals

Access/Use Permit from Municipal Road and Heavy Load Transportation

 

Municipal By-laws

 

Municipalities and Townships

 

 

  • Permits are required to install entrances and transport heavy loads on municipal roads

 

Approximately 70 per cent obtained

 

Pipeline Crossing Permit

 

 

Pipeline companies (oil and gas)

 

  • Permits are required to install access roads and conductors over existing oil and gas pipelines

Ongoing

 

Railway Crossing Permits

 

 

Canadian National and Goderich-Exeter Railway

 

  • Permits are required to cross railways with access roads and transmission lines

50 per cent obtained