Islington Transformer Station & Line Project

Hydro One is committed to energizing life for communities, people, and businesses across Ontario. As industry and businesses grow in the City of Toronto, so does the need for safe, clean and reliable power. In fall 2022, Hydro One initiated a Class Environmental Assessment (Class EA) to connect a new data facility, planned at 48 Lowe’s Place in Etobicoke, to the electricity grid.

Expected completion date

2025

Current project phase

Construction

We're here to help you

Project components include:

  • Building a new 230 kilovolt (kV) transformer station (TS) located on the facility’s property
  • Installing two new junction stations – which will help transition power from an overhead transmission line to an underground cable – within the existing Hydro One transmission line corridor, east of Islington Avenue and Rexdale Boulevard
  • Installing two new underground 230 kV transmission line cables between the new junctions and the new TS

On-going construction

Last updated March 19, 2025

As a part of the project we are installing two new underground 230 kV transmission line cables. This project will include closing roads and lanes as the crew will need to excavate and trench along the route path for initial equipment installation. The timeframes below are based on our current knowledge of the project and site working conditions.

Work zone Start date End date
Intersection of Allenby Ave and Burrard Rd September 2024 Completed
Burrard Rd (Allenby Ave to Boniface) End of March 2025 Early April 2025
Burrard Rd (Brigham Crt to Chilcot Ave) Beginning of February 2025 Middle of March 2025
Pine Point Park
Pine Point Park remains open
Parking lot closed until end of May
End of October 2024 End of May 2025
Conan Rd End of March 2025 End of May 2025
Intersection of Rexdale Blvd and Islington Ave (Night work only 8pm-6am) November 25, 2024 Completed
Rexdale Blvd (Bergamot Ave to 70 Rexdale Blvd) November 2024 Early April 2025
Rexdale Blvd and Silver Reign Dr Intersection
*Multiple crews will be working in this area
Rexdale Blvd (Islington Intersection to Westbound Bus Stop)
Rexdale Blvd (Westbound Bus Stop to Silver Reign Dr)


Beginning of March 2025
Beginning of March 2025


End of March 2025
End of April 2025
Rexdale Blvd Westbound Lanes (70 Rexdale Blvd to Hydro One Corridor) Mid January 2025 Mid March 2025
Rexdale Blvd Eastbound Lanes (Beneath Hydro One Corridor) End of March 2025 End of April 2025

Final construction activities will take place on Conan Rd, Allenby Ave, Burrard Rd., Chilcot Ave, and at the Rexdale Blvd. and Silver Reign Dr. intersection from mid-May intermittently to the end of August. Following the completion of this work, crews will complete cable testing for the month of September. During this time, motorist can expect small single lane closures from 7a.m-5p.m during the weekdays. After-hours and weekend work is not anticipated.

Important information

Please be advised that sidewalk closures may occur in the construction areas noted above. Alternative routes and signage will be posted around the closed areas for pedestrians.

Project route

Since the Class EA was initiated, Hydro One has been reviewing environmental and technical data and collected feedback on the study area shared in 2022. Based on this analysis and information, we have now selected a project route.


 
Public consultation

Please click the accordions below to view and download the associated materials.
 

Notice of Commencement — August 2022
 

Community open house series #1 — May 2023
 

Notice of upcoming open house – May 2023

Download the notice

In person community open house — May 2023

Download the panels

Selecting the route — May 2023

Download background information

Download detailed map

Community open house series #2 — February 2024
 

Notice of upcoming open house – February 2024

Download the notice

In person community open house— February 2024

Download the panels

Construction notice — June 2024
 

Notice of upcoming construction – June 2024

Download the notice

Project timeline

August 2022
Notice of Commencement
May 2023
Community open house #1
February 2024
Community open house #2
July 2024
Construction start
2025
Anticipated in-service date
Note: All dates are anticipated and could change based on project feedback.