Chatham-Kent to Lakeshore
As demand for electricity in Southwestern Ontario is anticipated to grow significantly over the next several years, Hydro One has commenced a Class Environmental Assessment to construct a new transmission line between Chatham-Kent to Lakeshore.


A safe and reliable power supply is essential to ensure southwestern Ontario can continue to grow now and into the future. That’s why Hydro One is proposing to construct a new double-circuit 230 kilovolt transmission line from our Chatham Switching Station located in the Municipality of Chatham-Kent to the future Lakeshore Switching Station, which will be located in the Municipality of Lakeshore. This new transmission line will help accommodate future electricity growth, improve reliability for homes and businesses and support local industries in the region at a time when it is needed most.

 
The proposed project will require the completion of a Class Environmental Assessment (Class EA), as well as Ontario Energy Board (OEB) approval (Leave-to-Construct application under Section 92 of the OEB Act).
 

Class Environmental Assessment

The Chatham to Lakeshore Line is subject to the Class Environmental Assessment for Minor Transmission Facilities (Hydro One, 2016) , in accordance with the Ontario Environmental Assessment Act. The Class EA is a streamlined planning process ensuring that applicable projects are planned and carried out in a manner that is efficient and environmentally acceptable.

 
Over the past year, Hydro One has been conducting a Class EA to build the new Chatham to Lakeshore Line. Through the Class EA process, we have assessed three route alternatives and associated variations by collecting environmental and technical information, as well as input from agencies, First Nations and Haudenosaunee communities, community members, elected officials, interest groups and businesses. Based on this information gathered and feedback received, Route Alternative 2A has been selected as the preferred route for the new transmission line, as shown on the maps below.

 
Consultation with the public, First Nations and Haudenosaunee communities, elected officials, municipal representatives, government agencies, and interest groups is an important part of the Class EA process.


Details of the review process will continue to be communicated through various channels, including consultation events , local newspapers, this project website, and via notifications to project stakeholders. As part of the consultation process, a draft Environmental Study Report (ESR) will be made available for a review period.
 

Click below to view an interactive map.


Interactive Map
 

Preferred Route Alternative

Chatham to Lakeshore - Area Map

Enlarge (.PDF)
West Portion

Revised Route Options Map West

Enlarge (.PDF)
Central Portion

Revised Route Options Map Central

Enlarge (.PDF)
East Portion

Revised Route Options Map East

Enlarge (.PDF)





Refined Route Alternatives

In October 2020, we made four refinements to the routes and identified a need to expand our Chatham Switching Station based on technical and environmental information learned.

Chatham-to-Lakeshore Local Study Area Map

Enlarge (.PDF)

West Portion

Route Options Map 1

Enlarge (.PDF)
Central Portion

Route Options Map 2

Enlarge (.PDF)
East Portion

Route Options Map 3

Enlarge (.PDF)





Initial Route Alternatives

Chatham-to-Lakeshore Local Study Area Map

Enlarge (.PDF)

West Portion

Route Options Map 1

Enlarge (.PDF)
Central Portion

Route Options Map 2

Enlarge (.PDF)
East Portion

Route Options Map 3

Enlarge (.PDF)






Anticipated Project Schedule

  • JANUARY2020
  • Notice of Commencement

  •  MARCH 2020
  • First Community Open House

    (Postponed due to COVID-19)

  •  MAY 2020
  • Virtual Information Session

    (Introduction of Project)

  • OCT/NOV
    2020
  • Virtual Open House & Live Discussion
    (Update on Project)

  • FEB/MAR2021
  • Virtual Open House & Live Discussion (Selection of Preferred Route)

  • LATE SPRING2021
  • Release of Draft Environmental Study Report for Review

  • 2023-
    2024
  • Proposed Construction Start*

  • 2024-
    2025
  • Proposed Line In-Service*

NOTE: All dates are anticipated and could change based on project feedback.
* In order to meet the energy needs of the region as quickly as possible, we are looking for opportunities to advance the construction start time to bring the new line into service at an earlier date.

 

Public Consultation

We invite you to join one of our upcoming engagement events for the Chatham to Lakeshore Line project. Please click the buttons below to view the associated materials.
 

Virtual Open House

Starting on February 25th, visit our virtual open house at chatham-to-lakeshore-openhouse.com to learn more about the preferred route, Class EA evaluation process, and next steps.


Virtual Open House

Live Virtual Discussion

On March 11th from 7:00-8:00 p.m., join us for a live virtual discussion with members of our project team where you will have an opportunity to ask questions.


Live Discussion


TO PARTICIPATE:

  1. Dial 1-800-785-1615 to join the call and listen to the presentation
  2. Visit hydroonemeeting.ca to register and view our live stream materials
  3. To submit a question in advance, please email your inquiry to Community.Relations@HydroOne.com

Download the Virtual Open House and Live Discussion Notice
Download the Virtual Open House and Live Discussion Newspaper Ad

Virtual Open House & Live Discussion
October/November 2020
Notice of Commencement
January 2020
Virtual Information Sessions
May 2020

Contact Us​

We are committed to listening to local communities every step of the way, and residents have an o​pportunity to provide feedback
or ask our project team a question by contacting Hydro One’s Community Relations at 1-877-345-6799 or Community.Relations@HydroOne.com.