D6 relocation project

We're empowering the thriving communities and businesses across Ontario and delivering on the growing need for safe, clean and reliable power.

Expected completion date: 2028

Current project phase: Planning - Environmental Assessment

We want to hear from you

The draft Environmental Study Report is now available for your review and comment from Friday, February 13 to Sunday, March 15, 2026.

Comment on the draft ESR
photo of a father and son playing together

Overview

We are planning to relocate approximately 25 kilometres of the line between Chalk River Junction (JCT) in the township of Laurentian Hills and Petawawa JCT in Petawawa.
 

The relocation of the line will allow crews to safely perform refurbishment work on equipment nearing the end of its service life and minimize impacts to military activities.

We are reinitiating the project Class Environmental Assessment for Transmission Facilities (Hydro One, 2024), in accordance with the Ontario Environmental Assessment Act for this project.

We’re here to help you

To provide comments or to be added to the project contact list, please call or email:

1-877-345-6799

Project map

Since fall 2021, Hydro One has collected environmental and technical information, as well as conducted a detailed constraints analysis to refine the proposed route.

D6 Relocation project route map

Environmental assessment process

The D6 Relocation Project is subject to an environmental assessment process, in accordance with the requirements of the Ontario Environmental Assessment Act. The environmental assessment will evaluate and determine a preferred route and assess the potential effects of the project.

Learn about the EA process
People sitting together talking

Our anticipated project schedule

Fall 2021
Class EA
Notice of Commencement
November 2021
Community Open House #1
Project pause
Constraints analysis and stakeholder discussions
April 2025
Reinitiate EA work
Share refined route alternative Community Open House #2
Spring/Summer 2025
Complete field surveys and Draft ESR
February 13 to March 15, 2026
Draft Environmental Study Report for public review and comment
Fall 2026
Finalize Class EA
Late 2026 or early 2027
Construction start
2028
Line in-service
*All dates are subject to change.

Public consultation

Consultation and engagement are a top priority for Hydro One. Help us ensure our project benefits your communities by getting in touch with us.
 

Draft Environmental Study Report (ESR)

The 30-day review and comment period for the draft Environmental Study Report is now open.

Start date: February 13, 2026 - End date: March 15, 2026

Hydro One values community input and will carefully consider all comments. Any concerns raised will be addressed before the ESR is finalized and submitted to the Ministry of Environment, Conservation and Parks (MECP). Once complete, the final ESR will be posted here.


Draft Environment Study Report resources

Open house resources

Alternative route maps

Notice of commencement

To provide comments or to be added to the project contact list, please connect with us

Phone Email

​​​​​​