Region Overview

Since the recent acquisition of Great Lakes Power (now Hydro One Sault Ste. Marie), this region is now solely supplied by Hydro One. The region supplies four distribution companies namely Chapleau PUC, Hydro One Networks Inc, PUC Distribution and Algoma Power Inc. The regional transmission system connects with provincial grid at Wawa TS and Mississagi TS, north of Thessalon.

Region's Local Distribution Companies
  • Algoma Power Inc.
  • Chapleau PUC
  • Hydro One Networks Inc.
  • PUC Distribution


Map: East Lake Superior

Current Status

The third Regional Planning cycle for this region was initiated with the publishing of a Needs Assessment report in October 2024 by Hydro One and followed by the release of a Scoping Assessment in February 2025 and Integrated Regional Resource Plan in July 2026 by the IESO. It is expected that the Regional Infrastructure Plan, which is the final step of the Regional Planning cycle, will be completed by February 2027. A local planning report to study transformation capacity of the Anjigami TS and Hollingsworth TS area was also completed by Hydro One in February 2026.

​ Accomplishment (Most Recent Shown First) Status Completion Date
Integrated Regional Resource Planning (3rd Cycle)
​Completed
July 2026
Local Planning Report (3rd Cycle)
​Completed
​February 2026
​Scoping Assessment (3rd Cycle)
​Completed
​January 2025
​Needs Assessment (3rd Cycle)
​Completed
​October 2024
Regional Infrastructure Planning ​(2nd Cycle)
Completed October 2021
Integrated Regional Resource Planning (2nd Cycle)
Completed April 2021
Local Planning (Batchawana and Goulais Bay Area) Completed February 2021
Scoping Assessment (2nd Cycle) Completed October 2019
Needs Assessment (2nd Cycle) Completed June 2019
​

*The completed reports are available below.

​

Rele​vant Documents​

Regional Infrastructure Plan (RIP)
Name Completion Date
East Lake Superior RIP - Report (2nd Cycle) October 2021

 

Integrated Regional Resource Planning (IRRP)
Name Completion Date
East Lake Superior IRRP – Report (3rd Cycle) July 2026
East Lake Superior IRRP – Report (2nd Cycle) April 2021
East Lake Superior IRRP – Appendices (2nd Cycle) April 2021

 

Needs Assessment (NA) & Scoping Assessment (SA)
Name Completion Date
East Lake Superior SA – Report (3rd cycle) January 2025​​​
East Lake Superior NA – Report (3rd cycle) October 2024​​​
East Lake Superior SA – Report (2nd Cycle) October 2019​​​
East Lake Superior NA - Report (2nd Cycle) June 2019

 

Local Planning (LP)
Name Completion Date
Local Planning Report - Anjigami TS & Hollingsworth TS Area February 2026
Local Planning Report - Supply Option Analysis for Batchawana and Goulais Bay Area February 2021
​
​