Region Overview

The Greater Bruce/Huron area is located to the west of the greater Toronto area in southwestern Ontario. The region includes the municipalities of Arran–Elderslie, Brockton, Kincardine, Northern Bruce Peninsula, and South Bruce. It also includes the township of Huron-Kinloss.

Region's Local Distribution Companies

  • Entegrus Powerlines Inc.
  • ERTH Power Corporation
  • Hydro One Networks Inc.
  • Festival Hydro Inc.
  • Wellington North Power Inc.
  • Westario Power Inc.


Map: Greater Bruce/Huron


Current Status

The third regional planning cycle for this region was kicked off in May 2024 beginning with the Needs Assessment (NA). The NA report for this region was completed in September 2024. It identified the needs in the region and recommended that some of the needs require further regional coordination, which will be reviewed during the scoping assessment phase.​

 
Accomplishment (Most Recent Shown First) Status Completion Date
Needs Assessment (3rd Cycle)
Completed September 2024
Regional Infrastructure Planning (2nd Cycle)
Completed April 2022
Integrated Regional Resource Planning (2nd Cycle)
Completed September 2021
Scoping Assessment (2nd Cycle)
Completed September 2019
Needs Assessment (2nd Cycle) Completed May 2019
Regional Infrastructure Planning Completed August 2017
Local Plan (Bruce Heavy Water B TS) Completed May 2017
Local Plan (LS7) Completed November 2016
Local Plan (Wingham TS) Completed October 2016
Needs Assessment Completed May 2016

*The completed reports are available below. 




Relevant Documents

Regional Infrastructure Planning (RIP)
Name Completion Date
Greater Bruce Huron RIP - Report (2nd cycle) April 2022
Greater Bruce Huron IRRP – Report & Appendices (2nd Cycle) September 2021
Greater Bruce Huron RIP - Report August 2017



Needs Assessment (NA) & Scoping Assessment (SA)
Name Completion Date
Greater Bruce Huron NA - Report (3rd cycle) September 2024
Greater Bruce Huron SA – Report (2nd Cycle) September 2019
Greater Bruce Huron NA - Report (2nd cycle)  May 2019
Greater Bruce Huron NA - Report  May 2016