Prospective Applicants may apply for a Preliminary Consultation for their project using Form A. Through the Preliminary Consultation process, we will assist applicants to identify the details of connecting a project to the grid such as: station capacity, station names, feeder designation, voltage, and potential point of connection.

 
Hydro One will respond to applicants within 15 days of receiving a completed Form A. If multiple requests are made, additional time will be required. We encourage prospective proponents to arrange for a Preliminary Consultation with our team if the point of connection is unknown.

 
Customers or companies can submit up to 3 Preliminary Consultation requests per calendar year at no charge. Any Preliminary Consultation Information Request (PCIR) beyond the limit will be charged.

 ​
Each PCIR request that exceeds the calendar year limit will be charged $50.00 + HST per request. Should you exceed the limit you will be notified, and we will provide payment details.
 ​