Customers or companies can submit up to 25 Pre-FIT Consultation requests and up to 25 Distribution Operating Map (DOM) requests at no charge. 


Please note effective December 14, 2015, any Pre-FIT Consultation or DOM request exceeding the 25th request (per type) will be charged an administrative fee.

The Pre-FIT Consultation is a service provided by us at no cost (up to 25 requests per customer or company; charges will apply for each request over 25) to provide the information the applicant needs in order to complete their IESO FIT Application Form.


The following​ charges will apply for each additional request over 25 requests per type:
  • DOM requests will be charged $12.00 + HST per request over 25

  • Pre-FIT requests will be charged $16.00 + HST per request over 25

Note: ​The total number of requests submitted are calculated over the lifetime of each customer, and calculated by type, i.e. customers can submit up to 25 free Pre-FIT Consultations and up to 25 free DOM requests before charges apply.


Prospective Applicants may apply for a Pre-FIT Consultation for their project using Form A (form found here). Through the Pre-FIT Consultation process, we will assist applicants to identify the details of connecting a project to the grid such as: station capacity, station names, feeder designation, voltage, and potential point of connection. 

If you would like to only obtain a portion of our Distribution Operating Map (DOM) related to your intended location, please complete the DOM Application Form at no cost (up to 25 requests per customer or company - charges will apply for each request over 25).


Ensure to be as precise as possible when completing the application, with specific regard to the following items:

  • GPS co-ordinates of your project location

  • Station and Feeder (if known)

  • Project Size (kW)


W
e will respond to applicants within 15 days of receiving a completed Form A. If multiple requests are made, additional time will be required. We encourage prospective proponents to arrange for a Pre-FIT Consultation with our team if the point of connection is unknown.