On-going construction
Last updated March 19, 2025
As a part of the project we are installing two new underground 230 kV transmission line cables.
This project will include closing roads and lanes as the crew will need to excavate and trench
along the route path for initial equipment installation. The timeframes below are based on our
current knowledge of the project and site working conditions.
Work zone |
Start date |
End date |
Intersection of Allenby Ave and Burrard Rd |
September 2024 |
Completed |
Burrard Rd (Allenby Ave to Boniface) |
End of March 2025 |
Early April 2025 |
Burrard Rd (Brigham Crt to Chilcot Ave) |
Beginning of February 2025 |
Middle of March 2025 |
Pine Point Park Pine Point Park remains open Parking lot closed until end of May |
End of October 2024 |
End of May 2025 |
Conan Rd |
End of March 2025 |
End of May 2025 |
Intersection of Rexdale Blvd and Islington Ave (Night work only
8pm-6am) |
November 25, 2024 |
Completed |
Rexdale Blvd (Bergamot Ave to 70 Rexdale Blvd) |
November 2024 |
Early April 2025 |
Rexdale Blvd and Silver Reign Dr Intersection *Multiple crews will be working in this area Rexdale Blvd (Islington Intersection to Westbound Bus Stop) Rexdale Blvd (Westbound Bus Stop to Silver Reign Dr) |
Beginning of March 2025 Beginning of March 2025 |
End of March 2025 End of April 2025 |
Rexdale Blvd Westbound Lanes (70 Rexdale Blvd to Hydro One
Corridor) |
Mid January 2025 |
Mid March 2025 |
Rexdale Blvd Eastbound Lanes (Beneath Hydro One Corridor) |
End of March 2025 |
End of April 2025 |