On-going construction
Last updated February 5, 2025
As a part of the project we are installing two new underground 230 kV transmission line cables.
This project will include closing roads and lanes as the crew will need to excavate and trench
along the route path for initial equipment installation. The timeframes below are based on our
current knowledge of the project and site working conditions.
Work zone |
Start date |
End date |
Intersection of Allenby Ave and Burrard Rd |
Completed |
Completed |
Burrard Rd (Allenby Ave to Brigham Crt) |
Beginning of December 2024 |
Late February 2025 |
Burrard Rd (Brigham Crt to Chilcot Ave) |
Beginning of February 2025 |
Beginning of March 2025 |
Intersection of Rexdale Blvd and Islington Ave (Night work only
8pm-6am) |
November 25, 2024 |
Mid January 2025 |
Rexdale Blvd (Bergamot Ave to 70 Rexdale Blvd) |
Completed |
Completed |
Rexdale Blvd (Islington Ave Intersection to Silver Reign Dr) |
Early February 2025 |
End of March 2025 |
Rexdale Blvd Westbound Lanes (70 Rexdale Blvd to Hydro One
Corridor) |
Mid January 2025 |
End of March 2025 |
Rexdale Blvd Eastbound Lanes (Beneath Hydro One Corridor) |
End of March 2025 |
End of April 2025 |