In December 2024, Hydro One completed construction - one year ahead of schedule - and energized a new doubble-circuit 230 kilovolt transmission line from our Chatham Switching Station in the Municipality of Chatham-Kent to our Lakeshore Switching Station in the Municipality of Lakeshore.
Current Project Phase
In-Service
Putting people, planet and communities first is vital to building a clean energy future in southwest Ontario. As part of our mission to manage project activities in an environmentally responsible and sustainable manner, Hydro One is undertaking the Chatham to Lakeshore Line Biodiversity Initiative to invest in the region's natural environment.
Hydro One is funding local projects or activities that focus on habitat creation and enhancement that can be enjoyed by generations for years to come.
For over 100 years, we’ve been powering the region and we will continue to provide safe and reliable electricity where and when it’s needed. As demand for electricity in southwestern Ontario is anticipated to grow significantly over the next several years, Hydro One is planning to begin construction in spring 2023 on a new double-circuit 230 kilovolt transmission line from our Chatham Switching Station in the Municipality of Chatham-Kent to our Lakeshore Switching Station in the Municipality of Lakeshore.
The project required the completion of a Class Environmental Assessment (Class EA) as well as Ontario Energy Board (OEB) approval (Leave-to-Construct application under Section 92 of the OEB Act). The EA was completed in October 2022 and Section 92 approval was received in November 2022.
NOTE: All dates are anticipated and could change based on project feedback. * In order to meet the energy needs of the region as quickly as possible, we are looking for opportunities to advance the construction start time to bring the new line into service at an earlier date.
The Chatham to Lakeshore Line was subject to the Class Environmental Assessment for Transmission Facilities (2022), in accordance with the Ontario Environmental Assessment Act. The Class EA is a streamlined planning process ensuring that applicable projects are planned and carried out in a manner that is efficient and environmentally acceptable. Hydro One began a Class EA in January 2020, which was completed and submitted to the Ministry of Environment, Conservation and Parks on October 28, 2022. To read the final environmental study report (ESR), click here.
Information about past engagement opportunities, including Class EA materials, can be viewed by clicking open the accordions below.
View the Final ESR
View Appendices A & B
View Appendices C & D
Download the Draft Environmental Study Report
Download the Appendix C and D of Draft Environmental Study Report
Download the Notice of Draft Environmental Study Report
Download the Notice of Commencement
Download the Newspaper Ad
View the Full Map
View the West Portion | Central Portion | East Portion
Download the update emailed to our project contact list.
Download our construction update emailed to our project contact list.
Click here to view our community drop-in invitation mailed to properties along the route.
Download our panels from our community drop-in in April 2023.
Listen to the Virtual Discussion
Download the Virtual Discussion Presentation
Download the Virtual Open House Panels
Download the Virtual Open House & Live Discussion Notice
Download the Virtual Open House & Live Discussion Newspaper Ad
Download the Indigenous Virtual Information Session Presentation from May 25 and 26
Download an audio recording of the Indigenous Virtual Information Session on May 25
Download an audio recording of the Indigenous Virtual Information Session on May 26
Download the video presentation from the Virtual Information Session on May 12: Part 1 | Part 2
Download the video presentation from the Virtual Information Session on May 14: Part 1 | Part 2
Download an audio recording of the Q&A from the Virtual Information Session on May 12
Download an audio recording of the Q&A from the Virtual Information Session on May 14
Download the Virtual Information Session Presentation from May 12 and 14
Download the Virtual Information Session Notice
Download the Virtual Information Session Newspaper Ad
Contact Hydro One Community Relations at 1-877-345-6799 or Community.Relations@HydroOne.com.